Skip to main content
RateWatt

Solar power plant, Florida

Sandy Creek Solar Power Plant, Florida

Sandy Creek Solar Power Plant is a 74.9 MW solar power plant in Bay County, Florida, operated by Duke Energy Florida, LLC, and it generated 166,565 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Florida, and its capacity factor sits at the 67th percentile of U.S. solar plants. By 2025 generation it ranks 2,746th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

74.9 MWNameplate capacity
25%Capacity factor, 2025, 67th percentile, on 74.9 MW net summer
0.1%Of FL generation, 2025
3 yearsAverage generator age, by MW

How hard does Sandy Creek Solar Power Plant run compared with other solar plants?

Sandy Creek Solar Power Plant had a capacity factor of 25% in 2025 on 74.9 MW of net summer capacity, the 67th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 93 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Sandy Creek Solar Power Plant25%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is Sandy Creek Solar Power Plant generating more or less than last year?

Generation at Sandy Creek Solar Power Plant rose 8.4% from 2024 to 2025, from 153,716 MWh to 166,565 MWh. Through August 2026 it is running 5.5% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024153,716
2025166,565
2026 through August121,922
2025, same months115,605
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202616,653
July 202617,481
June 202616,549
May 202615,479
April 202616,904
March 202616,263
February 202612,431
January 202610,162
December 20258,983
November 202512,249
October 202512,247
September 202517,481
August 202513,696
July 202516,179
June 202516,219
May 202517,112
April 202517,396
March 202515,239
February 202510,367
January 20259,397
December 20245,661
November 20246,202
October 202410,752
September 202410,618
August 202416,851
July 202415,707
June 202417,640
May 202418,130
April 202417,197
March 202414,282
February 202411,565
January 20249,111

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from Sandy Creek Solar Power Plant?

Sandy Creek Solar Power Plant made 0.1% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.1% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 84th largest of 331 plants in Florida, the 3,131st largest of 14,327 in the U.S. and the 607th largest of 7,223 solar plants. By 2025 generation it is the 118th largest of 313 generating plants in the state.

Sandy Creek Solar Power Plant within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)7579,9360.1%
Generation (MWh)166,565267,867,7350.1%
Solar capacity (MW)7512,2230.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at Sandy Creek Solar Power Plant, and when do they retire?

1 operable generator totals 74.9 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
PV1OperatingSolar Photovoltaic752022n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns Sandy Creek Solar Power Plant?

EIA lists no joint owners for Sandy Creek Solar Power Plant. Duke Energy Florida, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Duke Energy Florida, LLC charge homes?

Duke Energy Florida, LLC, the operator of Sandy Creek Solar Power Plant, had an average residential price of 18.36¢ per kWh and an average bill of $185 a month in 2025, 21% above the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
Duke Energy Florida, LLC18.36¢$18521% higher
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is Sandy Creek Solar Power Plant?

Sandy Creek Solar Power Plant is in Panama City, Bay County, Florida, at 30.1031° N, 85.4104° W. It sits in the Duke Energy Florida Inc balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Florida are similar in size?

Florida has 210 operable solar plants with 12,223 MW of capacity, and Sandy Creek Solar Power Plant's 74.9 MW is 1% of that.

Solar plants in Florida around this size
PlantCountyMW2025 MWh
Twin Rivers Solar Power PlantHamilton75166,044
Charlie Creek Solar Power PlantHardee75178,325
Bay Trail Solar Power PlantCitrus75163,460
Sandy Creek Solar Power PlantBay75166,565
Fort Green Solar Power PlantHardee75165,855
Hildreth Solar Power PlantSuwannee75184,669
Bay Ranch Solar Power PlantBay75179,275

Source: EIA Forms EIA-860 and EIA-923, 2025.