Wind power plant, Wyoming
Silver Sage Windpower wind power plant, Wyoming
Silver Sage Windpower is a 42 MW wind power plant in Laramie County, Wyoming, operated by Deriva Energy, and it generated 100,242 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Wyoming, and its capacity factor sits at the 29th percentile of U.S. wind plants. By 2025 generation it ranks 3,388th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Silver Sage Windpower plant run compared with other wind plants?
The Silver Sage Windpower plant had a capacity factor of 27% in 2025 on 42 MW of net summer capacity, the 29th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 99 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Silver Sage Windpower | 27% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Silver Sage Windpower plant generating more or less than last year?
Generation at Silver Sage Windpower fell 7.9% from 2024 to 2025, from 108,803 MWh to 100,242 MWh. Through August 2026 it is running 6.0% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 108,803 |
| 2025 | 100,242 |
| 2026 through August | 71,098 |
| 2025, same months | 67,099 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 4,468 |
| July 2026 | 4,103 |
| June 2026 | 7,358 |
| May 2026 | 8,151 |
| April 2026 | 9,581 |
| March 2026 | 12,913 |
| February 2026 | 10,651 |
| January 2026 | 13,873 |
| December 2025 | 13,731 |
| November 2025 | 12,262 |
| October 2025 | 4,496 |
| September 2025 | 2,654 |
| August 2025 | 5,082 |
| July 2025 | 5,018 |
| June 2025 | 2,596 |
| May 2025 | 8,848 |
| April 2025 | 9,261 |
| March 2025 | 12,494 |
| February 2025 | 10,651 |
| January 2025 | 13,149 |
| December 2024 | 14,076 |
| November 2024 | 12,713 |
| October 2024 | 7,573 |
| September 2024 | 5,857 |
| August 2024 | 4,660 |
| July 2024 | 3,345 |
| June 2024 | 9,654 |
| May 2024 | 10,472 |
| April 2024 | 10,436 |
| March 2024 | 9,039 |
| February 2024 | 11,034 |
| January 2024 | 9,944 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Silver Sage Windpower plant, and when do they retire?
1 operable generator totals 42 MW, with an average age of 16 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 42 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| SSW01 | Operating | Onshore Wind Turbine | 42 | 2009 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Silver Sage Windpower plant?
EIA lists no joint owners for Silver Sage Windpower. Deriva Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Silver Sage Windpower plant?
Silver Sage Windpower is in Cheyenne, Laramie County, Wyoming, at 41.1297° N, 105.0240° W. It sits in the Western Area Power Administration UGP West balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Wyoming are similar in size?
Wyoming has 28 operable wind plants with 4,707 MW of capacity, and Silver Sage Windpower's 42 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Pioneer Wind Park, LLC | Converse | 80 | 252,550 |
| Mountain Wind Power LLC | Uinta | 61 | 151,420 |
| Corriedale Wind Energy | Laramie | 53 | 214,312 |
| Silver Sage Windpower | Laramie | 42 | 100,242 |
| McFadden Ridge | Albany | 35 | 104,770 |
| Happy Jack Windpower Project | Laramie | 29 | 58,706 |
Source: EIA Forms EIA-860 and EIA-923, 2025.