Solar power plant, Nevada
Silver State Solar Power South power plant, Nevada
Silver State Solar Power South is a 260 MW solar power plant in Clark County, Nevada, operated by Silver State Solar Power South, LLC, and it generated 684,062 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.5% of the generation reported in Nevada, and its capacity factor sits at the 91st percentile of U.S. solar plants. By 2025 generation it ranks 1,009th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Silver State Solar Power South plant run compared with other solar plants?
The Silver State Solar Power South plant had a capacity factor of 30% in 2025 on 260 MW of net summer capacity, the 91st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 110 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Silver State Solar Power South | 30% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Silver State Solar Power South plant generating more or less than last year?
Generation at Silver State Solar Power South rose 8.7% from 2024 to 2025, from 629,339 MWh to 684,062 MWh. Through August 2026 it is running 12.8% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 629,339 |
| 2025 | 684,062 |
| 2026 through August | 446,198 |
| 2025, same months | 511,689 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 67,937 |
| July 2026 | 71,768 |
| June 2026 | 75,393 |
| May 2026 | 60,744 |
| April 2026 | 43,557 |
| March 2026 | 52,683 |
| February 2026 | 39,234 |
| January 2026 | 34,882 |
| December 2025 | 31,420 |
| November 2025 | 33,519 |
| October 2025 | 54,807 |
| September 2025 | 52,627 |
| August 2025 | 70,855 |
| July 2025 | 79,257 |
| June 2025 | 79,120 |
| May 2025 | 74,491 |
| April 2025 | 69,231 |
| March 2025 | 56,151 |
| February 2025 | 44,576 |
| January 2025 | 38,008 |
| December 2024 | 22,489 |
| November 2024 | 31,547 |
| October 2024 | 54,348 |
| September 2024 | 63,670 |
| August 2024 | 65,008 |
| July 2024 | 76,577 |
| June 2024 | 69,963 |
| May 2024 | 55,630 |
| April 2024 | 66,266 |
| March 2024 | 54,514 |
| February 2024 | 37,191 |
| January 2024 | 32,136 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Silver State Solar Power South plant, and when do they retire?
8 operable generators total 260 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 8 | 260 | 100% | none reported |
Every generator, 8 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BLK1 | Operating | Solar Photovoltaic | 26 | 2015 | n/a |
| BLK2 | Operating | Solar Photovoltaic | 28 | 2015 | n/a |
| BLK3 | Operating | Solar Photovoltaic | 37 | 2015 | n/a |
| BLK4 | Operating | Solar Photovoltaic | 36 | 2016 | n/a |
| BLK5 | Operating | Solar Photovoltaic | 35 | 2016 | n/a |
| BLK6 | Operating | Solar Photovoltaic | 37 | 2016 | n/a |
| BLK7 | Operating | Solar Photovoltaic | 35 | 2016 | n/a |
| BLK8 | Operating | Solar Photovoltaic | 26 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Silver State Solar Power South plant?
EIA lists no joint owners for Silver State Solar Power South. Silver State Solar Power South, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Silver State Solar Power South plant?
Silver State Solar Power South is in Primm Valley, Clark County, Nevada, at 35.6300° N, 115.3200° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Nevada are similar in size?
Nevada has 58 operable solar plants with 5,195 MW of capacity, and Silver State Solar Power South's 260 MW is 5% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Eagle Shadow Mountain Solar Farm | Clark | 300 | 901,380 |
| Silver State Solar Power South | Clark | 260 | 684,062 |
| Copper Mountain Solar 3 | Clark | 255 | 597,368 |
| Copper Mountain Solar 5, LLC | Clark | 252 | 691,408 |
| Moapa Southern Paiute | Clark | 250 | 611,738 |
Source: EIA Forms EIA-860 and EIA-923, 2025.