Spanish Peaks Solar power plant, Colorado

Spanish Peaks Solar is a 140 MW solar power plant in Las Animas County, Colorado, operated by Spanish Peaks Solar LLC, and it generated 344,231 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Colorado, and its capacity factor sits at the 83rd percentile of U.S. solar plants. By 2025 generation it ranks 1,797th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

140 MWNameplate capacity
28%Capacity factor, 2025, 83rd percentile, on 140 MW net summer
0.6%Of CO generation, 2025
1 yearAverage generator age, by MW

How hard does the Spanish Peaks Solar plant run compared with other solar plants?

The Spanish Peaks Solar plant had a capacity factor of 28% in 2025 on 140 MW of net summer capacity, the 83rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 102 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Spanish Peaks Solar28%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Spanish Peaks Solar plant generating more or less than last year?

Spanish Peaks Solar generated 344,231 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 6.0% behind the same months of 2025. 2024 has output for only 1 month, so the two years are not compared.

Net generation by period
PeriodMWh
20244,289
2025344,231
2026 through August231,380
2025, same months246,252
Monthly generation, Dec 2024 to Aug 2026
MonthMWh
August 20266,019
July 202637,758
June 202639,571
May 202628,323
April 202637,729
March 202632,640
February 202626,974
January 202622,366
December 202519,461
November 202518,570
October 202528,966
September 202530,982
August 202534,418
July 202537,374
June 202537,102
May 202536,580
April 202536,269
March 202529,303
February 202521,904
January 202513,302
December 20244,289

Source: EIA Form EIA-923, through August 2026.

How much of Colorado's electricity comes from the Spanish Peaks Solar plant?

Spanish Peaks Solar made 0.6% of the 55,830,894 MWh reported by Colorado plants in 2025, from 0.6% of the state's 22,712 MW of capacity. By capacity it is the 54th largest of 321 plants in Colorado, the 2,138th largest of 14,327 in the U.S. and the 327th largest of 7,223 solar plants. By 2025 generation it is the 41st largest of 292 generating plants in the state.

Spanish Peaks Solar within Colorado, 2025
MeasureThis plantColoradoShare
Capacity (MW)14022,7120.6%
Generation (MWh)344,23155,830,8940.6%
Solar capacity (MW)1403,2634.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Spanish Peaks Solar plant, and when do they retire?

1 operable generator totals 140 MW, with an average age of 1 year weighted by capacity at the end of 2025. 140 MW, 100% of operable capacity, has a planned retirement, the first in 2058.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1140100%2058
Capacity retiring by year
YearUnitsMW retiringShare of plant
20581140100%
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
47301OperatingSolar Photovoltaic14020242058

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Spanish Peaks Solar plant?

EIA lists no joint owners for Spanish Peaks Solar. Spanish Peaks Solar LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Spanish Peaks Solar plant?

Spanish Peaks Solar is in Trinidad, Las Animas County, Colorado, at 37.3780° N, 104.4750° W. It sits in the Public Service Company of Colorado balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Colorado are similar in size?

Colorado has 181 operable solar plants with 3,263 MW of capacity, and Spanish Peaks Solar's 140 MW is 4% of that.

Solar plants in Colorado around this size
PlantCountyMW2025 MWh
Pike Solar HybridEl Paso175446,179
Black Hollow SunWeld150114,700
Axial Basin SolarMoffat14547,132
Spanish Peaks SolarLas Animas140344,231
Comanche SolarPueblo120227,746
Dolores Canyon SolarDolores11021,452
Pioneer Solar (CO), LLCAdams80179,753

Source: EIA Forms EIA-860 and EIA-923, 2025.