Wind power plant, South Dakota

Sweetland Wind Farm, LLC power plant, South Dakota

Sweetland Wind Farm, LLC is a 200 MW wind power plant in Hand County, South Dakota, operated by Sweetland Wind Farm, LLC, and it generated 765,372 MWh in 2025 (Forms EIA-860 and EIA-923). That is 3.5% of the generation reported in South Dakota, and its capacity factor sits at the 87th percentile of U.S. wind plants. By 2025 generation it ranks 919th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

200 MWNameplate capacity
44%Capacity factor, 2025, 87th percentile, on 200 MW net summer
3.5%Of SD generation, 2025
2 yearsAverage generator age, by MW

How hard does the Sweetland Wind Farm, LLC plant run compared with other wind plants?

The Sweetland Wind Farm, LLC plant had a capacity factor of 44% in 2025 on 200 MW of net summer capacity, the 87th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 159 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Sweetland Wind Farm, LLC44%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Sweetland Wind Farm, LLC plant generating more or less than last year?

Generation at Sweetland Wind Farm, LLC fell 8.6% from 2024 to 2025, from 837,768 MWh to 765,372 MWh. Through August 2026 it is running 21.3% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024837,768
2025765,372
2026 through August559,918
2025, same months461,597
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202654,076
July 202666,978
June 202663,991
May 202679,233
April 202667,007
March 202686,059
February 202666,529
January 202676,045
December 202586,765
November 202566,636
October 202594,389
September 202555,985
August 202558,150
July 202536,289
June 202557,369
May 20252,736
April 202559,528
March 202585,337
February 202570,691
January 202591,497
December 202471,131
November 202467,568
October 202479,902
September 202480,434
August 202465,222
July 202443,477
June 202459,095
May 202473,372
April 202492,282
March 202481,411
February 202469,022
January 202454,852

Source: EIA Form EIA-923, through August 2026.

How much of South Dakota's electricity comes from the Sweetland Wind Farm, LLC plant?

Sweetland Wind Farm, LLC made 3.5% of the 21,865,712 MWh reported by South Dakota plants in 2025, from 2.6% of the state's 7,670 MW of capacity. Its share of output is 1.3 times its share of capacity. By capacity it is the 16th largest of 54 plants in South Dakota, the 1,524th largest of 14,327 in the U.S. and the 318th largest of 1,358 wind plants. By 2025 generation it is the 13th largest of 50 generating plants in the state.

Sweetland Wind Farm, LLC within South Dakota, 2025
MeasureThis plantSouth DakotaShare
Capacity (MW)2007,6702.6%
Generation (MWh)765,37221,865,7123.5%
Wind capacity (MW)2003,4575.8%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Sweetland Wind Farm, LLC plant, and when do they retire?

1 operable generator totals 200 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1200100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
SLWOperatingOnshore Wind Turbine2002023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Sweetland Wind Farm, LLC plant?

EIA lists no joint owners for Sweetland Wind Farm, LLC. Sweetland Wind Farm, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Sweetland Wind Farm, LLC plant?

Sweetland Wind Farm, LLC is in St. Lawrence, Hand County, South Dakota, at 44.3868° N, 98.8011° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in South Dakota are similar in size?

South Dakota has 25 operable wind plants with 3,457 MW of capacity, and Sweetland Wind Farm, LLC's 200 MW is 6% of that.

Wind plants in South Dakota around this size
PlantCountyMW2025 MWh
Crowned Ridge Wind II Energy CenterCodington201869,983
Crowned Ridge Wind Energy CenterCodington200811,568
Crocker Wind FarmClark200787,190
Sweetland Wind Farm, LLCHand200765,372
North Bend Wind Project, LLCHyde200883,234
Prairie Winds SD1Jerauld162358,076
Tatanka RidgeDeuel154593,774

Source: EIA Forms EIA-860 and EIA-923, 2025.