Skip to main content
RateWatt

Solar power plant, Texas

Wagyu solar power plant, Texas

Wagyu is a 120 MW solar power plant in Brazoria County, Texas, operated by Cubico USA, LLC, and it generated 235,421 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 44th percentile of U.S. solar plants. By 2025 generation it ranks 2,295th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

120 MWNameplate capacity
22%Capacity factor, 2025, 44th percentile, on 120 MW net summer
2,295thU.S. rank by generation, 2025
5 yearsAverage generator age, by MW

How hard does the Wagyu plant run compared with other solar plants?

The Wagyu plant had a capacity factor of 22% in 2025 on 120 MW of net summer capacity, the 44th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 82 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Wagyu22%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Wagyu plant generating more or less than last year?

Generation at Wagyu rose 13.0% from 2024 to 2025, from 208,266 MWh to 235,421 MWh. Through August 2026 it is running 11.8% behind the same months of 2025.

Net generation by period
PeriodMWh
2024208,266
2025235,421
2026 through August141,292
2025, same months160,114
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202626,044
July 202621,529
June 202619,938
May 202616,783
April 202613,031
March 202617,615
February 202613,885
January 202612,467
December 202510,800
November 202515,863
October 202523,190
September 202525,454
August 202524,422
July 202523,982
June 202525,253
May 202524,340
April 202521,470
March 202520,257
February 202511,376
January 20259,014
December 202411,153
November 202413,694
October 202421,593
September 202419,613
August 202424,163
July 202417,918
June 202424,471
May 202417,146
April 202417,298
March 202413,987
February 202415,158
January 202412,072

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Wagyu plant?

Wagyu made 0.0% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 468th largest of 1,023 plants in Texas, the 2,315th largest of 14,327 in the U.S. and the 379th largest of 7,223 solar plants. By 2025 generation it is the 430th largest of 816 generating plants in the state.

Wagyu within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)120195,9660.1%
Generation (MWh)235,421592,896,1760.0%
Solar capacity (MW)12030,7390.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Wagyu plant, and when do they retire?

1 operable generator totals 120 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1120100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1215OperatingSolar Photovoltaic1202020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Wagyu plant?

EIA lists no joint owners for Wagyu. Cubico USA, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Wagyu plant?

Wagyu is in Damon, Brazoria County, Texas, at 29.2423° N, 95.6581° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Wagyu's 120 MW is 0% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
Briar Creek Solar 1Navarro127219,455
Norton Solar FarmRunnels12559,847
Coniglio SolarFannin124205,760
WagyuBrazoria120235,421
Long Point SolarBrazoria120429
East Pecos SolarPecos119219,423
Bluebell Solar IISterling115254,548