Solar power plant, Texas
Bluebell Solar II power plant, Texas
Bluebell Solar II is a 115 MW solar power plant in Sterling County, Texas, operated by Bluebell Solar II, LLC, and it generated 254,548 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 66th percentile of U.S. solar plants. By 2025 generation it ranks 2,202nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Bluebell Solar II plant run compared with other solar plants?
The Bluebell Solar II plant had a capacity factor of 25% in 2025 on 115 MW of net summer capacity, the 66th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 92 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Bluebell Solar II | 25% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Bluebell Solar II plant generating more or less than last year?
Generation at Bluebell Solar II fell 4.3% from 2024 to 2025, from 266,119 MWh to 254,548 MWh. Through August 2026 it is running 1.1% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 266,119 |
| 2025 | 254,548 |
| 2026 through August | 179,447 |
| 2025, same months | 177,501 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 31,567 |
| July 2026 | 32,355 |
| June 2026 | 23,151 |
| May 2026 | 20,498 |
| April 2026 | 20,312 |
| March 2026 | 18,346 |
| February 2026 | 18,263 |
| January 2026 | 14,955 |
| December 2025 | 14,711 |
| November 2025 | 15,731 |
| October 2025 | 21,987 |
| September 2025 | 24,618 |
| August 2025 | 28,387 |
| July 2025 | 27,262 |
| June 2025 | 26,141 |
| May 2025 | 25,096 |
| April 2025 | 19,502 |
| March 2025 | 20,393 |
| February 2025 | 15,837 |
| January 2025 | 14,883 |
| December 2024 | 16,651 |
| November 2024 | 15,187 |
| October 2024 | 20,441 |
| September 2024 | 23,725 |
| August 2024 | 30,690 |
| July 2024 | 30,059 |
| June 2024 | 28,288 |
| May 2024 | 24,199 |
| April 2024 | 21,963 |
| March 2024 | 21,632 |
| February 2024 | 18,367 |
| January 2024 | 14,917 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Bluebell Solar II plant, and when do they retire?
1 operable generator totals 115 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 115 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BBS2 | Operating | Solar Photovoltaic | 115 | 2020 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Bluebell Solar II plant?
EIA lists no joint owners for Bluebell Solar II. Bluebell Solar II, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Bluebell Solar II plant?
Bluebell Solar II is in Sterling, Sterling County, Texas, at 31.8880° N, 100.8250° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Texas are similar in size?
Texas has 225 operable solar plants with 30,739 MW of capacity, and Bluebell Solar II's 115 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Wagyu | Brazoria | 120 | 235,421 |
| Long Point Solar | Brazoria | 120 | 429 |
| East Pecos Solar | Pecos | 119 | 219,423 |
| Bluebell Solar II | Sterling | 115 | 254,548 |
| Cutlass Solar 1 LLC | Fort Bend | 111 | 168,963 |
| Galloway 2 Solar Farm | Concho | 110 | 246,701 |
| Liberty County Solar Project | Liberty | 110 | 245,415 |
Source: EIA Forms EIA-860 and EIA-923, 2025.