Skip to main content
RateWatt

Solar power plant, Texas

Bluebell Solar II power plant, Texas

Bluebell Solar II is a 115 MW solar power plant in Sterling County, Texas, operated by Bluebell Solar II, LLC, and it generated 254,548 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 66th percentile of U.S. solar plants. By 2025 generation it ranks 2,202nd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

115 MWNameplate capacity
25%Capacity factor, 2025, 66th percentile, on 115 MW net summer
2,202ndU.S. rank by generation, 2025
5 yearsAverage generator age, by MW

How hard does the Bluebell Solar II plant run compared with other solar plants?

The Bluebell Solar II plant had a capacity factor of 25% in 2025 on 115 MW of net summer capacity, the 66th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 92 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Bluebell Solar II25%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Bluebell Solar II plant generating more or less than last year?

Generation at Bluebell Solar II fell 4.3% from 2024 to 2025, from 266,119 MWh to 254,548 MWh. Through August 2026 it is running 1.1% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024266,119
2025254,548
2026 through August179,447
2025, same months177,501
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202631,567
July 202632,355
June 202623,151
May 202620,498
April 202620,312
March 202618,346
February 202618,263
January 202614,955
December 202514,711
November 202515,731
October 202521,987
September 202524,618
August 202528,387
July 202527,262
June 202526,141
May 202525,096
April 202519,502
March 202520,393
February 202515,837
January 202514,883
December 202416,651
November 202415,187
October 202420,441
September 202423,725
August 202430,690
July 202430,059
June 202428,288
May 202424,199
April 202421,963
March 202421,632
February 202418,367
January 202414,917

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Bluebell Solar II plant?

Bluebell Solar II made 0.0% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 477th largest of 1,023 plants in Texas, the 2,386th largest of 14,327 in the U.S. and the 394th largest of 7,223 solar plants. By 2025 generation it is the 419th largest of 816 generating plants in the state.

Bluebell Solar II within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)115195,9660.1%
Generation (MWh)254,548592,896,1760.0%
Solar capacity (MW)11530,7390.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Bluebell Solar II plant, and when do they retire?

1 operable generator totals 115 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1115100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
BBS2OperatingSolar Photovoltaic1152020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Bluebell Solar II plant?

EIA lists no joint owners for Bluebell Solar II. Bluebell Solar II, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Bluebell Solar II plant?

Bluebell Solar II is in Sterling, Sterling County, Texas, at 31.8880° N, 100.8250° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Bluebell Solar II's 115 MW is 0% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
WagyuBrazoria120235,421
Long Point SolarBrazoria120429
East Pecos SolarPecos119219,423
Bluebell Solar IISterling115254,548
Cutlass Solar 1 LLCFort Bend111168,963
Galloway 2 Solar FarmConcho110246,701
Liberty County Solar ProjectLiberty110245,415

Source: EIA Forms EIA-860 and EIA-923, 2025.