Briar Creek Solar 1 is a 127 MW solar power plant in Navarro County, Texas, operated by Lightsource Renewable Energy Asset Management, LLC, and it generated 219,455 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 24th percentile of U.S. solar plants. By 2025 generation it ranks 2,368th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Briar Creek Solar 1 plant run compared with other solar plants?
The Briar Creek Solar 1 plant had a capacity factor of 20% in 2025 on 127 MW of net summer capacity, the 24th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 72 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Briar Creek Solar 1 | 20% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Briar Creek Solar 1 plant generating more or less than last year?
Generation at Briar Creek Solar 1 fell 6.0% from 2024 to 2025, from 233,577 MWh to 219,455 MWh. Through August 2026 it is running 8.4% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 233,577 |
| 2025 | 219,455 |
| 2026 through August | 166,152 |
| 2025, same months | 153,230 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 30,559 |
| July 2026 | 32,023 |
| June 2026 | 25,402 |
| May 2026 | 22,919 |
| April 2026 | 14,523 |
| March 2026 | 18,266 |
| February 2026 | 10,182 |
| January 2026 | 12,278 |
| December 2025 | 11,102 |
| November 2025 | 15,645 |
| October 2025 | 20,563 |
| September 2025 | 18,915 |
| August 2025 | 26,778 |
| July 2025 | 25,758 |
| June 2025 | 20,162 |
| May 2025 | 18,127 |
| April 2025 | 21,121 |
| March 2025 | 16,995 |
| February 2025 | 13,003 |
| January 2025 | 11,286 |
| December 2024 | 10,339 |
| November 2024 | 14,494 |
| October 2024 | 22,912 |
| September 2024 | 24,092 |
| August 2024 | 25,905 |
| July 2024 | 20,268 |
| June 2024 | 25,266 |
| May 2024 | 21,208 |
| April 2024 | 19,801 |
| March 2024 | 19,668 |
| February 2024 | 16,424 |
| January 2024 | 13,200 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Briar Creek Solar 1 plant, and when do they retire?
1 operable generator totals 127 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 127 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| TXBC1 | Operating | Solar Photovoltaic | 127 | 2021 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Briar Creek Solar 1 plant?
Briar Creek Solar 1, LLC is the only joint owner reported for Briar Creek Solar 1, with 100.0%. Lightsource Renewable Energy Asset Management, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Briar Creek Solar 1 plant?
Briar Creek Solar 1 is in Corsicana, Navarro County, Texas, at 32.0675° N, 96.5851° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Texas are similar in size?
Texas has 225 operable solar plants with 30,739 MW of capacity, and Briar Creek Solar 1's 127 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Elm Branch Solar 1 | Ellis | 135 | 253,009 |
| Elara Solar | Frio | 132 | 265,557 |
| Orange Grove | Jim Wells | 131 | 172,584 |
| Briar Creek Solar 1 | Navarro | 127 | 219,455 |
| Norton Solar Farm | Runnels | 125 | 59,847 |
| Coniglio Solar | Fannin | 124 | 205,760 |
| Wagyu | Brazoria | 120 | 235,421 |
Source: EIA Forms EIA-860 and EIA-923, 2025.