Solar power plant, California
Western Antelope Blue Sky B solar power plant, California
Western Antelope Blue Sky B is a 20 MW solar power plant in Los Angeles County, California, operated by AES Distributed Energy, and it generated 52,233 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 95th percentile of U.S. solar plants. By 2025 generation it ranks 4,046th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Western Antelope Blue Sky B plant run compared with other solar plants?
The Western Antelope Blue Sky B plant had a capacity factor of 31% in 2025 on 19 MW of net summer capacity, the 95th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 115 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Western Antelope Blue Sky B | 31% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Western Antelope Blue Sky B plant generating more or less than last year?
Generation at Western Antelope Blue Sky B rose 4.1% from 2024 to 2025, from 50,174 MWh to 52,233 MWh.
| Period | MWh |
|---|---|
| 2024 | 50,174 |
| 2025 | 52,233 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 2,532 |
| November 2025 | 2,391 |
| October 2025 | 4,065 |
| September 2025 | 4,667 |
| August 2025 | 5,677 |
| July 2025 | 6,547 |
| June 2025 | 6,281 |
| May 2025 | 5,928 |
| April 2025 | 4,797 |
| March 2025 | 2,759 |
| February 2025 | 3,439 |
| January 2025 | 3,150 |
| December 2024 | 2,602 |
| November 2024 | 2,877 |
| October 2024 | 3,982 |
| September 2024 | 4,789 |
| August 2024 | 5,615 |
| July 2024 | 5,591 |
| June 2024 | 5,871 |
| May 2024 | 5,584 |
| April 2024 | 3,712 |
| March 2024 | 3,785 |
| February 2024 | 2,935 |
| January 2024 | 2,831 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Western Antelope Blue Sky B plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WABSB | Operating | Solar Photovoltaic | 20 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Western Antelope Blue Sky B plant?
Western Antelope Blue Sky Ranch B is the only joint owner reported for Western Antelope Blue Sky B, with 100.0%. AES Distributed Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Western Antelope Blue Sky B plant?
Western Antelope Blue Sky B is in Lancaster, Los Angeles County, California, at 34.7321° N, 118.3136° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Western Antelope Blue Sky B's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Windhub Solar A LLC | Kern | 20 | 47,960 |
| Corcoran Solar 3 | Kings | 20 | 48,100 |
| Oro Loma | Fresno | 20 | 49,174 |
| Western Antelope Blue Sky B | Los Angeles | 20 | 52,233 |
| North Lancaster Ranch | Los Angeles | 20 | 38,557 |
| Central Antelope Dry Ranch C | Los Angeles | 20 | 38,946 |
| Adera Solar | Madera | 20 | 32,720 |
Source: EIA Forms EIA-860 and EIA-923, 2025.