North Lancaster Ranch is a 20 MW solar power plant in Los Angeles County, California, operated by AES Distributed Energy, and it generated 38,557 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 60th percentile of U.S. solar plants. By 2025 generation it ranks 4,413th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the North Lancaster Ranch plant run compared with other solar plants?
The North Lancaster Ranch plant had a capacity factor of 24% in 2025 on 18 MW of net summer capacity, the 60th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 89 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| North Lancaster Ranch | 24% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the North Lancaster Ranch plant generating more or less than last year?
Generation at North Lancaster Ranch rose 3.5% from 2024 to 2025, from 37,249 MWh to 38,557 MWh.
| Period | MWh |
|---|---|
| 2024 | 37,249 |
| 2025 | 38,557 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,579 |
| November 2025 | 1,821 |
| October 2025 | 3,475 |
| September 2025 | 3,477 |
| August 2025 | 3,806 |
| July 2025 | 4,109 |
| June 2025 | 3,960 |
| May 2025 | 4,070 |
| April 2025 | 4,066 |
| March 2025 | 3,472 |
| February 2025 | 2,786 |
| January 2025 | 1,936 |
| December 2024 | 1,612 |
| November 2024 | 2,062 |
| October 2024 | 3,237 |
| September 2024 | 3,597 |
| August 2024 | 3,897 |
| July 2024 | 3,792 |
| June 2024 | 3,779 |
| May 2024 | 4,090 |
| April 2024 | 3,700 |
| March 2024 | 3,384 |
| February 2024 | 2,334 |
| January 2024 | 1,765 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the North Lancaster Ranch plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| NLR | Operating | Solar Photovoltaic | 20 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the North Lancaster Ranch plant?
North Lancaster Ranch is the only joint owner reported for North Lancaster Ranch, with 100.0%. AES Distributed Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the North Lancaster Ranch plant?
North Lancaster Ranch is in Lancaster, Los Angeles County, California, at 34.7195° N, 118.3130° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and North Lancaster Ranch's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Corcoran Solar 3 | Kings | 20 | 48,100 |
| Oro Loma | Fresno | 20 | 49,174 |
| Western Antelope Blue Sky B | Los Angeles | 20 | 52,233 |
| North Lancaster Ranch | Los Angeles | 20 | 38,557 |
| Central Antelope Dry Ranch C | Los Angeles | 20 | 38,946 |
| Adera Solar | Madera | 20 | 32,720 |
| Frontier Solar LLC | Stanislaus | 20 | 47,900 |