Solar power plant, California
Adera Solar power plant, California
Adera Solar is a 20 MW solar power plant in Madera County, California, operated by AES Distributed Energy, and it generated 32,720 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 24th percentile of U.S. solar plants. By 2025 generation it ranks 4,632nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Adera Solar plant run compared with other solar plants?
The Adera Solar plant had a capacity factor of 20% in 2025 on 19 MW of net summer capacity, the 24th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 72 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Adera Solar | 20% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Adera Solar plant generating more or less than last year?
Generation at Adera Solar rose 89.6% from 2024 to 2025, from 17,258 MWh to 32,720 MWh.
| Period | MWh |
|---|---|
| 2024 | 17,258 |
| 2025 | 32,720 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 885 |
| November 2025 | 1,766 |
| October 2025 | 3,211 |
| September 2025 | 3,184 |
| August 2025 | 3,741 |
| July 2025 | 3,911 |
| June 2025 | 3,459 |
| May 2025 | 2,631 |
| April 2025 | 1,957 |
| March 2025 | 2,977 |
| February 2025 | 1,998 |
| January 2025 | 3,000 |
| December 2024 | 1,770 |
| November 2024 | 1,887 |
| October 2024 | 898 |
| September 2024 | 374 |
| August 2024 | 418 |
| July 2024 | 950 |
| June 2024 | 1,609 |
| May 2024 | 1,299 |
| April 2024 | 1,000 |
| March 2024 | 3,165 |
| February 2024 | 2,238 |
| January 2024 | 1,650 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Adera Solar plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| ADERA | Operating | Solar Photovoltaic | 20 | 2015 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Adera Solar plant?
EIA lists no joint owners for Adera Solar. AES Distributed Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Adera Solar plant?
Adera Solar is in Chowchilla, Madera County, California, at 37.1206° N, 120.3249° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Adera Solar's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Western Antelope Blue Sky B | Los Angeles | 20 | 52,233 |
| North Lancaster Ranch | Los Angeles | 20 | 38,557 |
| Central Antelope Dry Ranch C | Los Angeles | 20 | 38,946 |
| Adera Solar | Madera | 20 | 32,720 |
| Frontier Solar LLC | Stanislaus | 20 | 47,900 |
| CED Ducor 1 | Tulare | 20 | 52,334 |
| CED Ducor 2 | Tulare | 20 | 51,623 |
Source: EIA Forms EIA-860 and EIA-923, 2025.