Solar power plant, Virginia
Wythe County Solar power plant, Virginia
Wythe County Solar is a 75 MW solar power plant in Wythe County, Virginia, operated by RWE Clean Energy, and it generated 119,139 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Virginia, and its capacity factor sits at the 17th percentile of U.S. solar plants. By 2025 generation it ranks 3,209th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Wythe County Solar plant run compared with other solar plants?
The Wythe County Solar plant had a capacity factor of 18% in 2025 on 75 MW of net summer capacity, the 17th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 66 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Wythe County Solar | 18% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Wythe County Solar plant generating more or less than last year?
Wythe County Solar generated 119,139 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 41.6% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 119,139 |
| 2026 through August | 113,109 |
| 2025, same months | 79,886 |
Monthly generation, Mar 2025 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 16,271 |
| July 2026 | 15,923 |
| June 2026 | 18,699 |
| May 2026 | 15,468 |
| April 2026 | 17,592 |
| March 2026 | 12,656 |
| February 2026 | 9,298 |
| January 2026 | 7,202 |
| December 2025 | 5,674 |
| November 2025 | 9,072 |
| October 2025 | 11,157 |
| September 2025 | 13,350 |
| August 2025 | 12,942 |
| July 2025 | 18,354 |
| June 2025 | 18,562 |
| May 2025 | 15,431 |
| April 2025 | 14,597 |
| March 2025 | 0 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Wythe County Solar plant, and when do they retire?
1 operable generator totals 75 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 75 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GEN1 | Operating | Solar Photovoltaic | 75 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Wythe County Solar plant?
EIA lists no joint owners for Wythe County Solar. RWE Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Wythe County Solar plant?
Wythe County Solar is in Wythe County, Wythe County, Virginia, at 36.8760° N, 80.8370° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Virginia are similar in size?
Virginia has 141 operable solar plants with 5,163 MW of capacity, and Wythe County Solar's 75 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Altavista Solar | Campbell | 80 | 159,449 |
| Fountain Creek Solar | Greensville | 80 | 131,709 |
| Pleinmont Solar 1 | Spotsylvania | 75 | 141,653 |
| Wythe County Solar | Wythe | 75 | 119,139 |
| Alton Post Office Solar | Halifax | 75 | 136,967 |
| Foxglove Solar | Frederick | 75 | 125,844 |
| Powells Creek Solar - Hybrid | Halifax | 70 | 152,232 |
Source: EIA Forms EIA-860 and EIA-923, 2025.