Altavista Solar is a 80 MW solar power plant in Campbell County, Virginia, operated by Altavista Solar, LLC, and it generated 159,449 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Virginia, and its capacity factor sits at the 47th percentile of U.S. solar plants. By 2025 generation it ranks 2,810th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Altavista Solar plant run compared with other solar plants?
The Altavista Solar plant had a capacity factor of 23% in 2025 on 80 MW of net summer capacity, the 47th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 83 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Altavista Solar | 23% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Altavista Solar plant generating more or less than last year?
Generation at Altavista Solar fell 1.8% from 2024 to 2025, from 162,296 MWh to 159,449 MWh. Through August 2026 it is running 3.3% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 162,296 |
| 2025 | 159,449 |
| 2026 through August | 118,763 |
| 2025, same months | 114,922 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 15,154 |
| July 2026 | 15,765 |
| June 2026 | 18,420 |
| May 2026 | 17,400 |
| April 2026 | 17,880 |
| March 2026 | 15,112 |
| February 2026 | 10,448 |
| January 2026 | 8,584 |
| December 2025 | 7,155 |
| November 2025 | 10,891 |
| October 2025 | 13,611 |
| September 2025 | 12,870 |
| August 2025 | 12,839 |
| July 2025 | 16,426 |
| June 2025 | 18,121 |
| May 2025 | 15,438 |
| April 2025 | 15,284 |
| March 2025 | 16,143 |
| February 2025 | 9,904 |
| January 2025 | 10,767 |
| December 2024 | 7,643 |
| November 2024 | 9,631 |
| October 2024 | 14,706 |
| September 2024 | 11,889 |
| August 2024 | 13,790 |
| July 2024 | 15,310 |
| June 2024 | 17,656 |
| May 2024 | 12,023 |
| April 2024 | 23,388 |
| March 2024 | 14,714 |
| February 2024 | 11,803 |
| January 2024 | 9,743 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Altavista Solar plant, and when do they retire?
1 operable generator totals 80 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 80 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| ATLA | Operating | Solar Photovoltaic | 80 | 2021 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Altavista Solar plant?
EIA lists no joint owners for Altavista Solar. Altavista Solar, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Altavista Solar plant?
Altavista Solar is in Lynch Station, Campbell County, Virginia, at 37.1482° N, 79.3475° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Virginia are similar in size?
Virginia has 141 operable solar plants with 5,163 MW of capacity, and Altavista Solar's 80 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Grasshopper Solar | Mecklenburg | 80 | 122,467 |
| Water Strider Solar | Halifax | 80 | 162,948 |
| Greensville County Solar Project, LLC | Greensville | 80 | 138,886 |
| Altavista Solar | Campbell | 80 | 159,449 |
| Fountain Creek Solar | Greensville | 80 | 131,709 |
| Pleinmont Solar 1 | Spotsylvania | 75 | 141,653 |
| Wythe County Solar | Wythe | 75 | 119,139 |
Source: EIA Forms EIA-860 and EIA-923, 2025.