Solar power plant, Texas
Alamo 6 solar power plant, Texas
Alamo 6 is a 105 MW solar power plant in Pecos County, Texas, operated by BHE Renewables, LLC, and it generated 226,282 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 43rd percentile of U.S. solar plants. By 2025 generation it ranks 2,337th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Alamo 6 plant run compared with other solar plants?
The Alamo 6 plant had a capacity factor of 22% in 2025 on 116 MW of net summer capacity, the 43rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 81 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Alamo 6 | 22% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Alamo 6 plant generating more or less than last year?
Generation at Alamo 6 fell 4.9% from 2024 to 2025, from 237,908 MWh to 226,282 MWh. Through August 2026 it is running 12.6% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 237,908 |
| 2025 | 226,282 |
| 2026 through August | 136,283 |
| 2025, same months | 155,935 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 22,001 |
| July 2026 | 19,857 |
| June 2026 | 15,661 |
| May 2026 | 17,242 |
| April 2026 | 15,496 |
| March 2026 | 16,000 |
| February 2026 | 15,025 |
| January 2026 | 15,001 |
| December 2025 | 16,304 |
| November 2025 | 16,404 |
| October 2025 | 18,419 |
| September 2025 | 19,220 |
| August 2025 | 20,165 |
| July 2025 | 21,973 |
| June 2025 | 20,381 |
| May 2025 | 21,558 |
| April 2025 | 18,014 |
| March 2025 | 18,355 |
| February 2025 | 18,122 |
| January 2025 | 17,367 |
| December 2024 | 16,078 |
| November 2024 | 16,987 |
| October 2024 | 19,059 |
| September 2024 | 19,097 |
| August 2024 | 23,716 |
| July 2024 | 25,172 |
| June 2024 | 24,780 |
| May 2024 | 24,095 |
| April 2024 | 20,738 |
| March 2024 | 18,134 |
| February 2024 | 14,842 |
| January 2024 | 15,210 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Alamo 6 plant, and when do they retire?
1 operable generator totals 105 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 105 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| OCIA6 | Operating | Solar Photovoltaic | 105 | 2017 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Alamo 6 plant?
EIA lists no joint owners for Alamo 6. BHE Renewables, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Alamo 6 plant?
Alamo 6 is in Fort Stockton, Pecos County, Texas, at 30.9931° N, 102.2708° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Texas are similar in size?
Texas has 225 operable solar plants with 30,739 MW of capacity, and Alamo 6's 105 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Galloway 2 Solar Farm | Concho | 110 | 246,701 |
| Liberty County Solar Project | Liberty | 110 | 245,415 |
| Emerald Grove | Pecos | 108 | 256,324 |
| Alamo 6 | Pecos | 105 | 226,282 |
| Lamesa Solar | Dawson | 102 | 223,258 |
| OCI Alamo 5 LLC | Uvalde | 100 | 159,073 |
| OCI Alamo 7 LLC | Haskell | 100 | 231,602 |
Source: EIA Forms EIA-860 and EIA-923, 2025.