Beacon Solar Plant Site 5 is a 37.8 MW solar power plant in Kern County, California, operated by Sune Beacon Site 5, LLC, and it generated 88,452 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 76th percentile of U.S. solar plants. By 2025 generation it ranks 3,534th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

37.8 MWNameplate capacity
27%Capacity factor, 2025, 76th percentile, on 37.8 MW net summer
3,534thU.S. rank by generation, 2025
8 yearsAverage generator age, by MW

How hard does the Beacon Solar Plant Site 5 plant run compared with other solar plants?

The Beacon Solar Plant Site 5 plant had a capacity factor of 27% in 2025 on 37.8 MW of net summer capacity, the 76th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 98 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Beacon Solar Plant Site 527%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Beacon Solar Plant Site 5 plant generating more or less than last year?

Generation at Beacon Solar Plant Site 5 fell 4.8% from 2024 to 2025, from 92,879 MWh to 88,452 MWh. Through August 2026 it is running 9.9% behind the same months of 2025.

Net generation by period
PeriodMWh
202492,879
202588,452
2026 through August59,782
2025, same months66,366
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20267,757
July 20269,068
June 20268,743
May 20266,986
April 20268,632
March 20268,226
February 20265,686
January 20264,684
December 20253,922
November 20254,166
October 20256,833
September 20257,165
August 20258,232
July 20259,577
June 202510,705
May 202510,650
April 202510,048
March 20256,879
February 20255,402
January 20254,873
December 20244,099
November 20245,218
October 20247,570
September 20249,096
August 202410,823
July 202410,042
June 202410,651
May 202411,002
April 202410,457
March 20248,306
February 2024654
January 20244,961

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Beacon Solar Plant Site 5 plant?

Beacon Solar Plant Site 5 made 0.0% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 519th largest of 1,877 plants in California, the 4,178th largest of 14,327 in the U.S. and the 984th largest of 7,223 solar plants. By 2025 generation it is the 363rd largest of 1,608 generating plants in the state.

Beacon Solar Plant Site 5 within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)38107,4330.0%
Generation (MWh)88,452204,542,8980.0%
Solar capacity (MW)3824,6630.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Beacon Solar Plant Site 5 plant, and when do they retire?

1 operable generator totals 37.8 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s138100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
BEAC5OperatingSolar Photovoltaic382017n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Beacon Solar Plant Site 5 plant?

EIA lists no joint owners for Beacon Solar Plant Site 5. Sune Beacon Site 5, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Beacon Solar Plant Site 5 plant?

Beacon Solar Plant Site 5 is in Cantil, Kern County, California, at 35.2489° N, 118.0344° W. It sits in the Los Angeles Department of Water and Power balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Beacon Solar Plant Site 5's 37.8 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Elevation Solar CLos Angeles40102,483
Cuyama Solar, LLCSanta Barbara4063,174
Central 40Stanislaus4069,471
Beacon Solar Plant Site 5Kern3888,452
Edwards Sanborn S3Kern3888,107
Lost Hills/BlackwellKern3258,861
P66 Rodeo SolarContra Costa3036,993