Solar power plant, California
Lost Hills/Blackwell solar power plant, California
Lost Hills/Blackwell is a 32 MW solar power plant in Kern County, California, operated by Southern Power Co, and it generated 58,861 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 32nd percentile of U.S. solar plants. By 2025 generation it ranks 3,891st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Lost Hills/Blackwell plant run compared with other solar plants?
The Lost Hills/Blackwell plant had a capacity factor of 21% in 2025 on 32 MW of net summer capacity, the 32nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 77 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Lost Hills/Blackwell | 21% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Lost Hills/Blackwell plant generating more or less than last year?
Generation at Lost Hills/Blackwell fell 27.0% from 2024 to 2025, from 80,598 MWh to 58,861 MWh.
| Period | MWh |
|---|---|
| 2024 | 80,598 |
| 2025 | 58,861 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,676 |
| November 2025 | 3,167 |
| October 2025 | 4,544 |
| September 2025 | 6,153 |
| August 2025 | 8,083 |
| July 2025 | 8,337 |
| June 2025 | 7,300 |
| May 2025 | 7,020 |
| April 2025 | 3,339 |
| March 2025 | 2,318 |
| February 2025 | 2,958 |
| January 2025 | 3,966 |
| December 2024 | 2,373 |
| November 2024 | 3,765 |
| October 2024 | 5,628 |
| September 2024 | 7,726 |
| August 2024 | 9,722 |
| July 2024 | 10,293 |
| June 2024 | 10,483 |
| May 2024 | 9,675 |
| April 2024 | 7,758 |
| March 2024 | 5,318 |
| February 2024 | 4,704 |
| January 2024 | 3,153 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Lost Hills/Blackwell plant, and when do they retire?
2 operable generators total 32 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 2 | 32 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BLKW | Operating | Solar Photovoltaic | 12 | 2015 | n/a |
| LTHL | Operating | Solar Photovoltaic | 20 | 2015 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Lost Hills/Blackwell plant?
2 owners report shares in Lost Hills/Blackwell; Lost Hills Solar, LLC holds the largest named share, 62.5% or about 20 MW. Southern Power Co operates the plant.
| Owner | Share | MW | 2025 MWh, by share |
|---|---|---|---|
| Lost Hills Solar, LLC | 62.5% | 20 | 36,788 |
| Blackwell Solar, LLC | 37.5% | 12 | 22,073 |
Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.
Where is the Lost Hills/Blackwell plant?
Lost Hills/Blackwell is in Lost Hills, Kern County, California, at 35.6200° N, 119.8500° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Lost Hills/Blackwell's 32 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Central 40 | Stanislaus | 40 | 69,471 |
| Beacon Solar Plant Site 5 | Kern | 38 | 88,452 |
| Edwards Sanborn S3 | Kern | 38 | 88,107 |
| Lost Hills/Blackwell | Kern | 32 | 58,861 |
| P66 Rodeo Solar | Contra Costa | 30 | 36,993 |
| Seville 2 | Imperial | 30 | 78,279 |
| Midway Solar Farm II | Imperial | 30 | 36,099 |
Source: EIA Forms EIA-860 and EIA-923, 2025.