Solar power plant, California
Campo Verde Solar power plant, California
Campo Verde Solar is a 147 MW solar power plant in Imperial County, California, operated by Southern Power Co, and it generated 292,680 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 57th percentile of U.S. solar plants. By 2025 generation it ranks 2,010th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Campo Verde Solar plant run compared with other solar plants?
The Campo Verde Solar plant had a capacity factor of 24% in 2025 on 139 MW of net summer capacity, the 57th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 88 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Campo Verde Solar | 24% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Campo Verde Solar plant generating more or less than last year?
Generation at Campo Verde Solar fell 0.7% from 2024 to 2025, from 294,747 MWh to 292,680 MWh.
| Period | MWh |
|---|---|
| 2024 | 294,747 |
| 2025 | 292,680 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 17,864 |
| November 2025 | 10,120 |
| October 2025 | 28,602 |
| September 2025 | 27,606 |
| August 2025 | 28,482 |
| July 2025 | 31,057 |
| June 2025 | 29,049 |
| May 2025 | 28,318 |
| April 2025 | 25,590 |
| March 2025 | 21,107 |
| February 2025 | 21,654 |
| January 2025 | 23,231 |
| December 2024 | 17,621 |
| November 2024 | 78 |
| October 2024 | 29,397 |
| September 2024 | 31,209 |
| August 2024 | 31,857 |
| July 2024 | 30,002 |
| June 2024 | 31,691 |
| May 2024 | 29,090 |
| April 2024 | 23,439 |
| March 2024 | 24,300 |
| February 2024 | 23,491 |
| January 2024 | 22,572 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Campo Verde Solar plant, and when do they retire?
1 operable generator totals 147 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 147 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CVS1 | Operating | Solar Photovoltaic | 147 | 2013 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Campo Verde Solar plant?
Campo Verde Solar, LLC is the only joint owner reported for Campo Verde Solar, with 100.0%. Southern Power Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Campo Verde Solar plant?
Campo Verde Solar is in El Centro, Imperial County, California, at 32.7533° N, 115.7264° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Campo Verde Solar's 147 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Edwards Sanborn E4 | Kern | 149 | 326,084 |
| Imperial Solar Energy Center West | Imperial | 149 | 356,963 |
| Edwards Sanborn 1C | Kern | 148 | 37,973 |
| Campo Verde Solar | Imperial | 147 | 292,680 |
| Panoche Valley Solar Farm | San Benito | 140 | 271,653 |
| Rosamond South 1 | Kern | 140 | 164,725 |
| Edwards Sanborn E2 | Kern | 138 | 314,267 |
Source: EIA Forms EIA-860 and EIA-923, 2025.