Wind power plant, Texas
Colbeck's Corner, LLC wind power plant, Texas
Colbeck's Corner, LLC is a 200 MW wind power plant in Carson County, Texas, operated by RWE Clean Energy, and it generated 788,428 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 91st percentile of U.S. wind plants. By 2025 generation it ranks 894th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Colbeck's Corner, LLC plant run compared with other wind plants?
The Colbeck's Corner, LLC plant had a capacity factor of 45% in 2025 on 200 MW of net summer capacity, the 91st percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 164 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Colbeck's Corner, LLC | 45% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Colbeck's Corner, LLC plant generating more or less than last year?
Generation at Colbeck's Corner, LLC fell 7.2% from 2024 to 2025, from 849,934 MWh to 788,428 MWh. Through August 2026 it is running 11.7% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 849,934 |
| 2025 | 788,428 |
| 2026 through August | 572,063 |
| 2025, same months | 512,005 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 65,603 |
| July 2026 | 64,658 |
| June 2026 | 57,722 |
| May 2026 | 65,450 |
| April 2026 | 87,317 |
| March 2026 | 85,261 |
| February 2026 | 70,590 |
| January 2026 | 75,462 |
| December 2025 | 75,420 |
| November 2025 | 72,407 |
| October 2025 | 69,660 |
| September 2025 | 58,936 |
| August 2025 | 56,321 |
| July 2025 | 57,346 |
| June 2025 | 66,197 |
| May 2025 | 54,547 |
| April 2025 | 69,618 |
| March 2025 | 67,056 |
| February 2025 | 68,030 |
| January 2025 | 72,890 |
| December 2024 | 73,024 |
| November 2024 | 75,418 |
| October 2024 | 80,122 |
| September 2024 | 54,532 |
| August 2024 | 54,715 |
| July 2024 | 57,577 |
| June 2024 | 75,126 |
| May 2024 | 70,232 |
| April 2024 | 83,291 |
| March 2024 | 80,737 |
| February 2024 | 79,979 |
| January 2024 | 65,181 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Colbeck's Corner, LLC plant, and when do they retire?
1 operable generator totals 200 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 200 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GVII | Operating | Onshore Wind Turbine | 200 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Colbeck's Corner, LLC plant?
EIA lists no joint owners for Colbeck's Corner, LLC. RWE Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Colbeck's Corner, LLC plant?
Colbeck's Corner, LLC is in Groom, Carson County, Texas, at 35.2542° N, 101.1866° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Colbeck's Corner, LLC's 200 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Los Vientos Wind 1A | Cameron | 200 | 408,298 |
| Longhorn Wind | Briscoe | 200 | 696,969 |
| TX Hereford Wind | Deaf Smith | 200 | 526,300 |
| Colbeck's Corner, LLC | Carson | 200 | 788,428 |
| Los Vientos Windpower III | Starr | 200 | 447,710 |
| Los Vientos Windpower IV | Starr | 200 | 421,995 |
| South Plains Wind Phase I | Floyd | 200 | 677,007 |
Source: EIA Forms EIA-860 and EIA-923, 2025.