Skip to main content
RateWatt

Wind power plant, Texas

Los Vientos Windpower III wind power plant, Texas

Los Vientos Windpower III is a 200 MW wind power plant in Starr County, Texas, operated by Deriva Energy, and it generated 447,710 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 24th percentile of U.S. wind plants. By 2025 generation it ranks 1,461st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

200 MWNameplate capacity
26%Capacity factor, 2025, 24th percentile, on 200 MW net summer
0.1%Of TX generation, 2025
10 yearsAverage generator age, by MW

How hard does the Los Vientos Windpower III plant run compared with other wind plants?

The Los Vientos Windpower III plant had a capacity factor of 26% in 2025 on 200 MW of net summer capacity, the 24th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 93 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Los Vientos Windpower III26%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Los Vientos Windpower III plant generating more or less than last year?

Generation at Los Vientos Windpower III fell 7.9% from 2024 to 2025, from 486,054 MWh to 447,710 MWh. Through August 2026 it is running 1.5% behind the same months of 2025.

Net generation by period
PeriodMWh
2024486,054
2025447,710
2026 through August337,192
2025, same months342,191
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202638,916
July 202647,167
June 202636,446
May 202636,797
April 202647,684
March 202663,562
February 202635,743
January 202630,877
December 202530,663
November 202548,270
October 202514,034
September 202512,552
August 202538,277
July 202560,448
June 202527,126
May 202540,068
April 202554,258
March 202552,712
February 202535,743
January 202533,559
December 202431,939
November 202435,194
October 202421,790
September 202424,570
August 202429,498
July 202444,651
June 202451,555
May 202453,447
April 202455,794
March 202452,362
February 202441,174
January 202444,080

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Los Vientos Windpower III plant?

Los Vientos Windpower III made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 302nd largest of 1,023 plants in Texas, the 1,524th largest of 14,327 in the U.S. and the 297th largest of 1,358 wind plants. By 2025 generation it is the 299th largest of 816 generating plants in the state.

Los Vientos Windpower III within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)200195,9660.1%
Generation (MWh)447,710592,896,1760.1%
Wind capacity (MW)20043,9420.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Los Vientos Windpower III plant, and when do they retire?

1 operable generator totals 200 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1200100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingOnshore Wind Turbine2002015n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Los Vientos Windpower III plant?

Los Vientos Windpower III, LLC is the only joint owner reported for Los Vientos Windpower III, with 100.0%. Deriva Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Los Vientos Windpower III plant?

Los Vientos Windpower III is in Rio Grande City, Starr County, Texas, at 26.3886° N, 98.8061° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Texas are similar in size?

Texas has 228 operable wind plants with 43,942 MW of capacity, and Los Vientos Windpower III's 200 MW is 0% of that.

Wind plants in Texas around this size
PlantCountyMW2025 MWh
Longhorn WindBriscoe200696,969
TX Hereford WindDeaf Smith200526,300
Colbeck's Corner, LLCCarson200788,428
Los Vientos Windpower IIIStarr200447,710
Los Vientos Windpower IVStarr200421,995
South Plains Wind Phase IFloyd200677,007
Javelina Wind Energy II, LLCWebb200761,596

Source: EIA Forms EIA-860 and EIA-923, 2025.