Crane Creek Wind Energy Center, Iowa

Crane Creek Wind Energy Center is a 99 MW wind power plant in Howard County, Iowa, operated by Wisconsin Public Service Corp, and it generated 284,033 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in Iowa, and its capacity factor sits at the 50th percentile of U.S. wind plants. By 2025 generation it ranks 2,046th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

99 MWNameplate capacity
33%Capacity factor, 2025, 50th percentile, on 99 MW net summer
0.4%Of IA generation, 2025
16 yearsAverage generator age, by MW

How hard does the Crane Creek Wind Energy Center plant run compared with other wind plants?

The Crane Creek Wind Energy Center plant had a capacity factor of 33% in 2025 on 99 MW of net summer capacity, the 50th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 120 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Crane Creek Wind Energy Center33%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Crane Creek Wind Energy Center plant generating more or less than last year?

Generation at Crane Creek Wind Energy Center fell 6.0% from 2024 to 2025, from 302,016 MWh to 284,033 MWh.

Net generation by period
PeriodMWh
2024302,016
2025284,033
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202528,946
November 202528,605
October 202522,752
September 202512,982
August 20259,624
July 202511,482
June 202520,112
May 202521,986
April 202532,329
March 202534,307
February 202526,092
January 202534,816
December 202424,189
November 202429,286
October 202433,061
September 202418,332
August 202414,576
July 202411,057
June 202422,206
May 202423,265
April 202438,338
March 202435,919
February 202429,254
January 202422,533

Source: EIA Form EIA-923, through August 2026.

How much of Iowa's electricity comes from the Crane Creek Wind Energy Center plant?

Crane Creek Wind Energy Center made 0.4% of the 74,502,373 MWh reported by Iowa plants in 2025, from 0.4% of the state's 24,817 MW of capacity. By capacity it is the 83rd largest of 306 plants in Iowa, the 2,738th largest of 14,327 in the U.S. and the 692nd largest of 1,358 wind plants. By 2025 generation it is the 67th largest of 283 generating plants in the state.

Crane Creek Wind Energy Center within Iowa, 2025
MeasureThis plantIowaShare
Capacity (MW)9924,8170.4%
Generation (MWh)284,03374,502,3730.4%
Wind capacity (MW)9913,4100.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Crane Creek Wind Energy Center plant, and when do they retire?

1 operable generator totals 99 MW, with an average age of 16 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s199100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine992009n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Crane Creek Wind Energy Center plant?

EIA lists no joint owners for Crane Creek Wind Energy Center. Wisconsin Public Service Corp operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Wisconsin Public Service Corp charge homes?

Wisconsin Public Service Corp, the operator of Crane Creek Wind Energy Center, had an average residential price of 17.20¢ per kWh and an average bill of $106 a month in 2025 in Wisconsin.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Iowa
Wisconsin Public Service Corp17.20¢$106other state
Iowa average13.62¢$117
U.S. average17.23¢$15126% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Crane Creek Wind Energy Center plant?

Crane Creek Wind Energy Center is in Riceville, Howard County, Iowa, at 43.3978° N, 92.4736° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Iowa are similar in size?

Iowa has 123 operable wind plants with 13,410 MW of capacity, and Crane Creek Wind Energy Center's 99 MW is 1% of that.

Wind plants in Iowa around this size
PlantCountyMW2025 MWh
Heartland Divide Wind Project, LLCAudubon104425,811
Lost Lakes Wind Farm LLCDickinson100270,128
New Harvest Wind Project LLCCrawford100262,989
Crane Creek Wind Energy CenterHoward99284,033
Franklin County Wind FarmFranklin99270,522
Osceola Windpower LLCOsceola98393,767
Hancock County Wind Energy CenterHancock98255,466