Solar power plant, California
Edwards Sanborn E1A solar power plant, California
Edwards Sanborn E1A is a 293 MW power plant, 149 MW of it solar, in Kern County, California, operated by Terra-Gen Operating Co-Hybrid, and it generated 332,363 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in California, and its capacity factor sits at the 75th percentile of U.S. solar plants. By 2025 generation it ranks 1,838th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Edwards Sanborn E1A plant run compared with other solar plants?
The Edwards Sanborn E1A plant's solar units had a capacity factor of 27% in 2025 on 149 MW of net summer capacity, the 75th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 97 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Edwards Sanborn E1A | 27% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.
Is the Edwards Sanborn E1A plant generating more or less than last year?
Generation at Edwards Sanborn E1A rose 1.6% from 2024 to 2025, from 327,194 MWh to 332,363 MWh. Through August 2026 it is running 8.3% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 327,194 |
| 2025 | 332,363 |
| 2026 through August | 226,158 |
| 2025, same months | 246,678 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 34,521 |
| July 2026 | 35,191 |
| June 2026 | 40,278 |
| May 2026 | 34,036 |
| April 2026 | 23,563 |
| March 2026 | 25,274 |
| February 2026 | 17,076 |
| January 2026 | 16,219 |
| December 2025 | 14,281 |
| November 2025 | 15,183 |
| October 2025 | 26,324 |
| September 2025 | 29,897 |
| August 2025 | 35,731 |
| July 2025 | 40,806 |
| June 2025 | 39,153 |
| May 2025 | 37,442 |
| April 2025 | 35,436 |
| March 2025 | 21,358 |
| February 2025 | 18,982 |
| January 2025 | 17,770 |
| December 2024 | 14,032 |
| November 2024 | 17,662 |
| October 2024 | 24,822 |
| September 2024 | 29,350 |
| August 2024 | 35,584 |
| July 2024 | 37,074 |
| June 2024 | 40,037 |
| May 2024 | 40,442 |
| April 2024 | 32,540 |
| March 2024 | 22,702 |
| February 2024 | 17,614 |
| January 2024 | 15,335 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Edwards Sanborn E1A plant, and when do they retire?
2 operable generators total 293 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 2 | 293 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BESS | Operating | Batteries | 144 | 2022 | n/a |
| PV | Operating | Solar Photovoltaic | 149 | 2022 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Edwards Sanborn E1A plant?
EIA lists no joint owners for Edwards Sanborn E1A. Terra-Gen Operating Co-Hybrid operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the Edwards Sanborn E1A plant use?
Edwards Sanborn E1A has capacity on 2 fuels: 51% solar and 49% battery and pumped storage. In 2025, solar made 105% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Solar | 149 | 50.9% | 347,607 |
| Battery and pumped storage | 144 | 49.1% | -15,244 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Edwards Sanborn E1A plant?
Edwards Sanborn E1A is in Mojave, Kern County, California, at 34.9619° N, 118.1242° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Edwards Sanborn E1A's 149 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Fifth Standard Solar PV, LLC (Hybrid) | Fresno | 150 | 327,093 |
| Baldy Mesa Solar & Storage | San Bernardino | 150 | 303,251 |
| Northern Orchard Solar PV, LLC | Kern | 150 | 210,871 |
| Edwards Sanborn E1A | Kern | 149 | 347,607 |
| Edwards Sanborn E4 | Kern | 149 | 326,084 |
| Imperial Solar Energy Center West | Imperial | 149 | 356,963 |
| Edwards Sanborn 1C | Kern | 148 | 37,973 |
Source: EIA Forms EIA-860 and EIA-923, 2025.