Skip to main content
RateWatt

Solar power plant, California

Lockhart Solar PV II power plant, California

Lockhart Solar PV II is a 144 MW power plant, 84.4 MW of it solar, in San Bernardino County, California, operated by Terra-Gen Operating Co-Solar, and it generated 204,180 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 96th percentile of U.S. solar plants. By 2025 generation it ranks 2,464th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

144 MWNameplate capacity
32%Capacity factor, 2025, solar units, 96th percentile, on 75 MW net summer
0.1%Of CA generation, 2025
1 yearAverage generator age, by MW

How hard does the Lockhart Solar PV II plant run compared with other solar plants?

The Lockhart Solar PV II plant's solar units had a capacity factor of 32% in 2025 on 75 MW of net summer capacity, the 96th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 115 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Lockhart Solar PV II32%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.

Is the Lockhart Solar PV II plant generating more or less than last year?

Generation at Lockhart Solar PV II rose 10.0% from 2024 to 2025, from 185,584 MWh to 204,180 MWh. Through August 2026 it is running 5.4% behind the same months of 2025.

Net generation by period
PeriodMWh
2024185,584
2025204,180
2026 through August143,715
2025, same months151,991
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202618,006
July 202620,971
June 202623,319
May 202623,257
April 202619,160
March 202617,527
February 202611,593
January 20269,882
December 20258,798
November 202510,049
October 202515,209
September 202518,133
August 202521,922
July 202525,147
June 202523,815
May 202522,791
April 202519,541
March 202514,444
February 202512,740
January 202511,591
December 20247,759
November 202411,809
October 202415,545
September 202418,996
August 202422,216
July 202421,353
June 202417,000
May 202421,341
April 202419,449
March 202413,557
February 20248,371
January 20248,188

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Lockhart Solar PV II plant?

Lockhart Solar PV II made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.1% of the state's 107,433 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 194th largest of 1,877 plants in California, the 2,111th largest of 14,327 in the U.S. and the 516th largest of 7,223 solar plants on its solar units alone. By 2025 generation it is the 258th largest of 1,608 generating plants in the state.

Lockhart Solar PV II within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)144107,4330.1%
Generation (MWh)204,180204,542,8980.1%
Solar capacity (MW)8424,6630.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Lockhart Solar PV II plant, and when do they retire?

2 operable generators total 144 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s2144100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
LOC2OperatingSolar Photovoltaic842023n/a
LHC2OperatingBatteries602025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Lockhart Solar PV II plant?

EIA lists no joint owners for Lockhart Solar PV II. Terra-Gen Operating Co-Solar operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What fuels does the Lockhart Solar PV II plant use?

Lockhart Solar PV II has capacity on 2 fuels: 59% solar and 41% battery and pumped storage. In 2025, solar made 102% of its output.

Capacity and 2025 generation by fuel
FuelMWShare2025 MWh
Solar8458.6%207,421
Battery and pumped storage6041.4%-3,241

Source: EIA Forms EIA-860 and EIA-923, 2025.

Where is the Lockhart Solar PV II plant?

Lockhart Solar PV II is in Hinkley, San Bernardino County, California, at 35.0435° N, 117.3489° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Lockhart Solar PV II's 84.4 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Springbok 3 Solar Farm HybridKern90251,125
Resurgence SolarSan Bernardino90266,026
Solverde 1Los Angeles85205,460
Lockhart Solar PV IISan Bernardino84207,421
Desert Harvest, LLCRiverside80231,035
RE Astoria 2Kern75144,825
Colgreen North Shore Solar FarmRiverside75117,832

Source: EIA Forms EIA-860 and EIA-923, 2025.