Solar power plant, California
RE Astoria 2 solar power plant, California
RE Astoria 2 is a 75 MW solar power plant in Kern County, California, operated by RE Astoria 2 LLC, and it generated 144,825 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 41st percentile of U.S. solar plants. By 2025 generation it ranks 2,954th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the RE Astoria 2 plant run compared with other solar plants?
The RE Astoria 2 plant had a capacity factor of 22% in 2025 on 75 MW of net summer capacity, the 41st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 80 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| RE Astoria 2 | 22% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the RE Astoria 2 plant generating more or less than last year?
Generation at RE Astoria 2 fell 7.2% from 2024 to 2025, from 156,005 MWh to 144,825 MWh. Through August 2026 it is running 44.1% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 156,005 |
| 2025 | 144,825 |
| 2026 through August | 146,515 |
| 2025, same months | 101,670 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 20,285 |
| July 2026 | 21,860 |
| June 2026 | 23,817 |
| May 2026 | 23,255 |
| April 2026 | 20,371 |
| March 2026 | 18,100 |
| February 2026 | 10,606 |
| January 2026 | 8,221 |
| December 2025 | 7,134 |
| November 2025 | 7,832 |
| October 2025 | 12,893 |
| September 2025 | 15,296 |
| August 2025 | 18,525 |
| July 2025 | 19,657 |
| June 2025 | 15,330 |
| May 2025 | 13,565 |
| April 2025 | 9,696 |
| March 2025 | 9,597 |
| February 2025 | 7,102 |
| January 2025 | 8,198 |
| December 2024 | 7,499 |
| November 2024 | 8,549 |
| October 2024 | 11,761 |
| September 2024 | 15,903 |
| August 2024 | 21,079 |
| July 2024 | 21,246 |
| June 2024 | 22,080 |
| May 2024 | 14,931 |
| April 2024 | 8,322 |
| March 2024 | 6,372 |
| February 2024 | 8,687 |
| January 2024 | 9,576 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the RE Astoria 2 plant, and when do they retire?
1 operable generator totals 75 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 75 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| ASTR2 | Operating | Solar Photovoltaic | 75 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the RE Astoria 2 plant?
EIA lists no joint owners for RE Astoria 2. RE Astoria 2 LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the RE Astoria 2 plant?
RE Astoria 2 is in Rosamond, Kern County, California, at 34.8366° N, 118.4802° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and RE Astoria 2's 75 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Solverde 1 | Los Angeles | 85 | 205,460 |
| Lockhart Solar PV II | San Bernardino | 84 | 207,421 |
| Desert Harvest, LLC | Riverside | 80 | 231,035 |
| RE Astoria 2 | Kern | 75 | 144,825 |
| Colgreen North Shore Solar Farm | Riverside | 75 | 117,832 |
| Titan Solar 1 (CA) | Imperial | 70 | 130,368 |
| Desert Harvest II LLC | Riverside | 70 | 183,786 |
Source: EIA Forms EIA-860 and EIA-923, 2025.