Solar power plant, California
Springbok 3 Solar Farm Hybrid power plant, California
Springbok 3 Solar Farm Hybrid is a 91.5 MW power plant, 90 MW of it solar, in Kern County, California, operated by 64KT 8me LLC, and it generated 251,125 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 96th percentile of U.S. solar plants. By 2025 generation it ranks 2,225th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Springbok 3 Solar Farm Hybrid plant run compared with other solar plants?
The Springbok 3 Solar Farm Hybrid plant's solar units had a capacity factor of 32% in 2025 on 90 MW of net summer capacity, the 96th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 116 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Springbok 3 Solar Farm Hybrid | 32% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.
Is the Springbok 3 Solar Farm Hybrid plant generating more or less than last year?
Generation at Springbok 3 Solar Farm Hybrid rose 1.8% from 2024 to 2025, from 246,675 MWh to 251,125 MWh. Through August 2026 it is running 14.1% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 246,675 |
| 2025 | 251,125 |
| 2026 through August | 159,773 |
| 2025, same months | 185,968 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 21,959 |
| July 2026 | 24,151 |
| June 2026 | 22,042 |
| May 2026 | 23,762 |
| April 2026 | 24,660 |
| March 2026 | 21,953 |
| February 2026 | 9,511 |
| January 2026 | 11,735 |
| December 2025 | 11,274 |
| November 2025 | 11,549 |
| October 2025 | 20,215 |
| September 2025 | 22,119 |
| August 2025 | 25,600 |
| July 2025 | 28,862 |
| June 2025 | 28,156 |
| May 2025 | 25,548 |
| April 2025 | 26,836 |
| March 2025 | 21,843 |
| February 2025 | 15,596 |
| January 2025 | 13,527 |
| December 2024 | 11,814 |
| November 2024 | 13,862 |
| October 2024 | 18,791 |
| September 2024 | 22,798 |
| August 2024 | 26,098 |
| July 2024 | 25,495 |
| June 2024 | 26,016 |
| May 2024 | 28,074 |
| April 2024 | 26,249 |
| March 2024 | 20,473 |
| February 2024 | 14,189 |
| January 2024 | 12,816 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Springbok 3 Solar Farm Hybrid plant, and when do they retire?
2 operable generators total 91.5 MW, with an average age of 6 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 2 | 92 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| SB3BS | Operating | Batteries | 2 | 2019 | n/a |
| SB3SF | Operating | Solar Photovoltaic | 90 | 2019 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Springbok 3 Solar Farm Hybrid plant?
EIA lists no joint owners for Springbok 3 Solar Farm Hybrid. 64KT 8me LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the Springbok 3 Solar Farm Hybrid plant use?
Springbok 3 Solar Farm Hybrid has capacity on 2 fuels: 98% solar and 2% battery and pumped storage. In 2025, solar made 100% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Solar | 90 | 98.4% | 251,125 |
| Battery and pumped storage | 2 | 1.6% | 0 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the Springbok 3 Solar Farm Hybrid plant?
Springbok 3 Solar Farm Hybrid is in Cantil, Kern County, California, at 35.1712° N, 118.0017° W. It sits in the Los Angeles Department of Water and Power balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Springbok 3 Solar Farm Hybrid's 90 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Hudson - High Desert Hybrid | San Bernardino | 100 | 298,031 |
| Rabbitbrush Solar, LLC | Kern | 100 | 249,029 |
| Sandrini Solar 100 | Kern | 100 | 235,587 |
| Springbok 3 Solar Farm Hybrid | Kern | 90 | 251,125 |
| Resurgence Solar | San Bernardino | 90 | 266,026 |
| Solverde 1 | Los Angeles | 85 | 205,460 |
| Lockhart Solar PV II | San Bernardino | 84 | 207,421 |
Source: EIA Forms EIA-860 and EIA-923, 2025.