Skip to main content
RateWatt

Solar power plant, Nevada

Luning Energy solar power plant, Nevada

Luning Energy is a 50 MW solar power plant in Mineral County, Nevada, operated by Liberty Utilities (CalPeco Electric) LLC, and it generated 102,129 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Nevada, and its capacity factor sits at the 52nd percentile of U.S. solar plants. By 2025 generation it ranks 3,370th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

50 MWNameplate capacity
23%Capacity factor, 2025, 52nd percentile, on 50 MW net summer
0.2%Of NV generation, 2025
8 yearsAverage generator age, by MW

How hard does the Luning Energy plant run compared with other solar plants?

The Luning Energy plant had a capacity factor of 23% in 2025 on 50 MW of net summer capacity, the 52nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 85 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Luning Energy23%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Luning Energy plant generating more or less than last year?

Generation at Luning Energy rose 1.7% from 2024 to 2025, from 100,464 MWh to 102,129 MWh. Through August 2026 it is running 6.1% behind the same months of 2025.

Net generation by period
PeriodMWh
2024100,464
2025102,129
2026 through August72,049
2025, same months76,691
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202610,067
July 20269,535
June 202610,563
May 202611,676
April 202610,274
March 20269,174
February 20265,694
January 20265,066
December 20254,489
November 20254,897
October 20257,413
September 20258,639
August 202510,410
July 202511,969
June 202511,963
May 202511,926
April 202510,448
March 20258,524
February 20256,085
January 20255,366
December 20244,584
November 20244,918
October 20246,655
September 20248,086
August 20249,305
July 202410,055
June 202412,842
May 202412,898
April 202411,055
March 20248,577
February 20246,351
January 20245,138

Source: EIA Form EIA-923, through August 2026.

How much of Nevada's electricity comes from the Luning Energy plant?

Luning Energy made 0.2% of the 45,180,066 MWh reported by Nevada plants in 2025, from 0.3% of the state's 18,959 MW of capacity. By capacity it is the 57th largest of 117 plants in Nevada, the 3,754th largest of 14,327 in the U.S. and the 878th largest of 7,223 solar plants. By 2025 generation it is the 58th largest of 112 generating plants in the state.

Luning Energy within Nevada, 2025
MeasureThis plantNevadaShare
Capacity (MW)5018,9590.3%
Generation (MWh)102,12945,180,0660.2%
Solar capacity (MW)505,1951.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Luning Energy plant, and when do they retire?

1 operable generator totals 50 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s150100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
LNINGOperatingSolar Photovoltaic502017n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Luning Energy plant?

EIA lists no joint owners for Luning Energy. Liberty Utilities (CalPeco Electric) LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Luning Energy plant?

Luning Energy is in Luning, Mineral County, Nevada, at 38.5469° N, 118.1916° W. It sits in the Nevada Power Company balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Nevada are similar in size?

Nevada has 58 operable solar plants with 5,195 MW of capacity, and Luning Energy's 50 MW is 1% of that.

Solar plants in Nevada around this size
PlantCountyMW2025 MWh
Turquoise Nevada, LLCWashoe60108,716
Silver State Solar Power NorthClark52113,384
Boulder Solar II, LLCClark50110,547
Luning EnergyMineral50102,129
Techren Solar VClark50107,986
CM48Clark4889,650
Spectrum Solar PV Power ProjectClark3081,819

Source: EIA Forms EIA-860 and EIA-923, 2025.