Skip to main content
RateWatt

Solar power plant, California

Solar Gen 2 Solar Facility, California

Solar Gen 2 Solar Facility is a 163 MW solar power plant in Imperial County, California, operated by Southern Power Co, and it generated 376,661 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in California, and its capacity factor sits at the 85th percentile of U.S. solar plants. By 2025 generation it ranks 1,668th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

163 MWNameplate capacity
29%Capacity factor, 2025, 85th percentile, on 150 MW net summer
0.2%Of CA generation, 2025
11 yearsAverage generator age, by MW

How hard does the Solar Gen 2 Solar Facility plant run compared with other solar plants?

The Solar Gen 2 Solar Facility plant had a capacity factor of 29% in 2025 on 150 MW of net summer capacity, the 85th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 105 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Solar Gen 2 Solar Facility29%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Solar Gen 2 Solar Facility plant generating more or less than last year?

Generation at Solar Gen 2 Solar Facility rose 3.4% from 2024 to 2025, from 364,207 MWh to 376,661 MWh.

Net generation by period
PeriodMWh
2024364,207
2025376,661
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202518,411
November 202519,945
October 202530,854
September 202533,453
August 202537,552
July 202542,355
June 202541,841
May 202539,157
April 202539,414
March 202529,849
February 202523,523
January 202520,307
December 202417,586
November 202416,424
October 202428,185
September 202433,155
August 202438,040
July 202441,004
June 202443,198
May 202443,695
April 202433,710
March 202426,125
February 202424,998
January 202418,087

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Solar Gen 2 Solar Facility plant?

Solar Gen 2 Solar Facility made 0.2% of the 204,542,898 MWh reported by California plants in 2025, from 0.2% of the state's 107,433 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 165th largest of 1,877 plants in California, the 1,867th largest of 14,327 in the U.S. and the 237th largest of 7,223 solar plants. By 2025 generation it is the 121st largest of 1,608 generating plants in the state.

Solar Gen 2 Solar Facility within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)163107,4330.2%
Generation (MWh)376,661204,542,8980.2%
Solar capacity (MW)16324,6630.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Solar Gen 2 Solar Facility plant, and when do they retire?

3 operable generators total 163 MW, with an average age of 11 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s3163100%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
ALHMOperatingSolar Photovoltaic542014n/a
ARKOperatingSolar Photovoltaic542014n/a
SONROperatingSolar Photovoltaic542014n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Solar Gen 2 Solar Facility plant?

SG2 Imperial Valley, LLC is the only joint owner reported for Solar Gen 2 Solar Facility, with 100.0%. Southern Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Solar Gen 2 Solar Facility plant?

Solar Gen 2 Solar Facility is in Calipatria, Imperial County, California, at 33.0800° N, 115.4700° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Solar Gen 2 Solar Facility's 163 MW is 1% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Daggett 2San Bernardino182539,807
Centinela Solar EnergyImperial175448,552
Chaparral SpringsKern174425,521
Solar Gen 2 Solar FacilityImperial163376,661
Rancho Seco Solar II, LLCSacramento160275,130
Springbok Solar Farm 2Kern155397,111
Edwards Sanborn E1BKern154371,792

Source: EIA Forms EIA-860 and EIA-923, 2025.