Skip to main content
RateWatt

Solar power plant, Texas

Old 300 Solar Center, LLC power plant, Texas

Old 300 Solar Center, LLC is a 430 MW solar power plant in Fort Bend County, Texas, operated by Old 300 Solar Center, LLC, and it generated 901,599 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Texas, and its capacity factor sits at the 57th percentile of U.S. solar plants. By 2025 generation it ranks 787th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

430 MWNameplate capacity
24%Capacity factor, 2025, 57th percentile, on 430 MW net summer
0.2%Of TX generation, 2025
1 yearAverage generator age, by MW

How hard does the Old 300 Solar Center, LLC plant run compared with other solar plants?

The Old 300 Solar Center, LLC plant had a capacity factor of 24% in 2025 on 430 MW of net summer capacity, the 57th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 87 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Old 300 Solar Center, LLC24%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Old 300 Solar Center, LLC plant generating more or less than last year?

Generation at Old 300 Solar Center, LLC rose 12.9% from 2024 to 2025, from 798,531 MWh to 901,599 MWh. Through August 2026 it is running level with the same months of 2025.

Net generation by period
PeriodMWh
2024798,531
2025901,599
2026 through August686,429
2025, same months686,271
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026113,124
July 2026101,992
June 202698,023
May 202695,050
April 202654,511
March 202687,656
February 202675,455
January 202660,618
December 202521,376
November 202529,802
October 202562,894
September 2025101,256
August 202596,154
July 202599,677
June 2025103,922
May 2025101,823
April 202594,772
March 202591,677
February 202550,140
January 202548,106
December 202451,312
November 202459,121
October 202486,269
September 202472,171
August 202493,596
July 202475,515
June 202493,078
May 202461,684
April 202458,777
March 202451,045
February 202450,687
January 202445,276

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Old 300 Solar Center, LLC plant?

Old 300 Solar Center, LLC made 0.2% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.2% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 120th largest of 1,023 plants in Texas, the 816th largest of 14,327 in the U.S. and the 15th largest of 7,223 solar plants. By 2025 generation it is the 133rd largest of 816 generating plants in the state.

Old 300 Solar Center, LLC within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)430195,9660.2%
Generation (MWh)901,599592,896,1760.2%
Solar capacity (MW)43030,7391.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Old 300 Solar Center, LLC plant, and when do they retire?

1 operable generator totals 430 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1430100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
2222OperatingSolar Photovoltaic4302024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Old 300 Solar Center, LLC plant?

EIA lists no joint owners for Old 300 Solar Center, LLC. Old 300 Solar Center, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Old 300 Solar Center, LLC plant?

Old 300 Solar Center, LLC is in Needville, Fort Bend County, Texas, at 29.3335° N, 95.8254° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Old 300 Solar Center, LLC's 430 MW is 1% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
Aktina SolarWharton500930,128
Parliament SolarWaller48049,192
Mockingbird Solar CenterLamar471928,383
Old 300 Solar Center, LLCFort Bend430901,599
2W Permian Solar Project HybridAndrews4201,007,398
Ash Creek SolarHill409405,591
Sequoia 1Eastland40121,120

Source: EIA Forms EIA-860 and EIA-923, 2025.